Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 23380 REL 6: 2007-398-00 CAP MANASTASH CONSTRUCTION SERVICES - FISHPRO
Project Number:
Title:
Yakima Basinwide Tributary Passage and Flow
Stage:
Implementation
Area:
Province Subbasin %
Columbia Plateau Yakima 100.00%
Contract Number:
23380 REL 6
Contract Title:
2007-398-00 CAP MANASTASH CONSTRUCTION SERVICES - FISHPRO
Contract Continuation:
Previous: Next:
23380 REL 4: 2003-001-00 CAP MANASTASH FINAL DESIGN/CONST. MGMT
  • 54966: 2007-398-00 CAP MANASTASH CONSTRUCTION SERVICES
Contract Status:
Closed
Contract Description:
Manastash Creek is an important Yakima River tributary, which drains a 100-square mile watershed in Kittitas County lying west of Ellensburg, Washington.     Approximately 30 miles of potential high-quality salmonid habitat remains in the upper portions of the watershed, which lie primarily within the Wenatchee National Forest.  

On March 25, 1999, NMFS listed the Middle Columbia River Basin steelhead ESU as "threatened," effective May 24, 1999.   64 Fed. Reg. 14,517.  This ESU includes the Yakima River and its tributaries.  On February 16, 2000, NMFS designated the Yakima River and its tributaries as critical habitat for Middle Columbia River steelhead.  65 Fed. Reg. 7779.

In February 2001, the Washington Environmental Council (WEC) sent the WDFW, and the largest private water users on Manastash Creek, the Kittitas Reclamation District (KRD) and the Westside Irrigating Company (Westside)  a draft notice of intent to sue under Section 11(g) of the Endangered Species Act (ESA), 16 U.S.C. § 1540(g).  The draft notice alleged that continued operation of the six irrigation diversions on Manastash Creek would result in an unlawful "take" of threatened steelhead under Section 9 of the ESA, 16 U.S.C. § 1538(a). The WEC contended that prior to the advent of irrigated agriculture, Manastash Creek produced steelhead, coho and spring Chinook salmon.

WEC invited the water users to work in a collaborative process which would protect both threatened fish and the future of Manastash Creek related irrigated agriculture in Kittitas County. The collaborative efforts proceeded and a relationship of cooperation and trust between the parties has developed.  The WEC's goal is to eliminate fish passage barriers, eliminate unscreened diversions and improve instream flows.  The irrigators' goal is to cooperate in the improvement of fish habitat on Manastash Creek while at the same time remaining whole and being able to manage and operate their land and water rights as a viable agricultural enterprise.  

A watershed restoration plan, along with an MOA among all parties and a plan for implementing flow improvements, are the fruits of these many months of collaborative efforts.  The overall restoration involves two efforts.  In one, the major water diversions on Manastash Creek will be reconstructed so as to eliminate manmade barriers or impediments to fish passage and all unscreened diversions.  This work will involve  consolidation of 4 of these diversions at the MWDA site- MWDA, Reed, Anderson and Hatfield.  The consolidated diversions will be decommissioned and the sites restored. The goal of the flow enhancement portion of the project is the restoration of more natural summer/fall flows in the lower part of Manastash Creek while at the same time protecting the vested water rights of the Manastash Creek water users. This piece is already underway under contract with KCCD.

BPA has approximately  $2.0 million through the F&W program to address fish screening and passage at the Manastash diversions (Phase 1). Earlier efforts included a water conservation study that laid out conceptual plans for remedies to the fish passage problems, along with rough schematics and cost estimates, initial permitting activities and pre-design.  This release with FishPro is to finalize planning, permitting  and design for the fish passage improvement effort, assist BPA with access appraisals and provide construction management for the MWDA and Keats-Jensen Facilities.
Account Type(s):
Capital
Contract Start Date:
06/01/2008
Contract End Date:
12/31/2011
Current Contract Value:
$2,044,963
Expenditures:
$2,044,963

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

Env. Compliance Lead:
Contract Contractor:
Work Order Task(s):
Contract Type:
Release
Pricing Method:
Time and Materials
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Brenda Aguirre Bonneville Power Administration No Env. Compliance Lead baguirre@bpa.gov (503) 230-5928
Ed Donahue Fishpro, Inc. Yes Supervisor ed.donahue@hdrinc.com (253) 858-5262
Michael Garello Fishpro, Inc. Yes Contract Manager mike.garello@hdrinc.com (253) 858-5635
Sherry Jeffery HDR Engineering, Inc. Yes Administrative Contact sherry.jeffery@hdrinc.com (253) 858-5262
Peter Lofy Bonneville Power Administration Yes F&W Approver ptlofy@bpa.gov (503) 230-4193
Jay Marcotte Bonneville Power Administration Yes COR jgmarcotte@bpa.gov (503) 230-3943
Kristi Van Leuven Bonneville Power Administration Yes Contracting Officer kjvleuven@bpa.gov (503) 230-3605


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Efficiently managed project A: 119. Manage and Administer Project 12/31/2011 12/30/2011
100% design and specs B: 175. Final Design 12/31/2011 12/30/2011
Submittal of Permit Applications C: 165. Assist in EC documentation completion 06/30/2008 07/15/2008
Effectively managed construction project D: 100. Construction Management for MWDA (Consolidated) facilities 05/13/2011 06/28/2011
Effectively managed construction project E: 100. Construction Management for Keach/Jensen facilities 12/15/2011 12/30/2011
Completed O&M plan F: 174. Produce O&M plan/manual for MWDA and K-J facilities 06/10/2011 06/10/2011
appraisals complete G: 172. Provide appraisals for project easements 10/01/2008 09/30/2008
Fish Screen installed I: 69. Install Fish Screen - MWDA Facility 04/08/2011 06/28/2011
Fish Screen installed J: 69. Install Fish Screen - KJ Facility 12/08/2011 12/30/2011
placeholder K: 69. Install Fish Screen - Barnes Facility 01/08/2010 03/22/2010
roughened channel (Fish Passage Structure) installed L: 184. Install Fish Passage Structure - MWDA Facility 04/30/2010 01/22/2010
Fish Passage Structure installed M: 184. Install Fish Passage Structure - KJ Facility 12/15/2011 12/30/2011
Placeholder for EC N: 184. Install Fish Passage Structure - Barnes Facility 01/08/2010 03/22/2010
preparation complete for barrier removal P: 157. CCR22486 Site Recon and Data Collection for Abandoned Dam Removal 12/15/2011 12/15/2011
design completed for water control structure replacement Q: 175. CCR22486 Design Water Control Structure at the Barnes Road Diversion 09/30/2011 09/30/2011

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Steelhead (O. mykiss) - Middle Columbia River DPS (Threatened)
  • 3 instances of WE 69 Install Fish Screen
  • 3 instances of WE 184 Install Fish Passage Structure
  • 1 instance of WE 174 Produce Plan
  • 2 instances of WE 175 Produce Design
  • 1 instance of WE 157 Collect/Generate/Validate Field and Lab Data

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 119 Manage and Administer Project 02/09/2007
B 175 Final Design 02/09/2007
C 165 Assist in EC documentation completion 02/09/2007
D 100 Construction Management for MWDA (Consolidated) facilities 02/09/2007
E 100 Construction Management for Keach/Jensen facilities 02/09/2007
F 174 Produce O&M plan/manual for MWDA and K-J facilities 02/09/2007
G 172 Provide appraisals for project easements 02/09/2007
H 185 Periodic Status Reports for BPA 02/09/2007
I 69 Install Fish Screen - MWDA Facility 09/10/2008
J 69 Install Fish Screen - KJ Facility 09/10/2008
K 69 Install Fish Screen - Barnes Facility 10/14/2008
L 184 Install Fish Passage Structure - MWDA Facility 09/10/2008
M 184 Install Fish Passage Structure - KJ Facility 09/10/2008
N 184 Install Fish Passage Structure - Barnes Facility 10/14/2008
O 132 No progress report required 02/09/2007
P 157 CCR22486 Site Recon and Data Collection for Abandoned Dam Removal 06/01/2008
Q 175 CCR22486 Design Water Control Structure at the Barnes Road Diversion 06/01/2008